WATCH: How Indian Railways sets a new design and time record

Date:

Railways set a new record, the East Coast Railway of Indian Railways-Visakhapatnam Division made a subway at a busy railway track between Pendurthi and Kothavalasa line in just four and a half hours. Until now it was a manned level crossing.

ALSO READ: Railways and IT ministry ink pact to allow bookings via 2.9 lakh Common Service…

The work was sanctioned in 2017, the limited height subway work, which comprised the installation of 20 segments of 1.5m width, was started in over four and a half hours back. The Railways authorities used 16 heavy duty excavators, three heavy duty cranes, five tippers (truck), 1,000 sandbags, four hydra machines, heavyweight jacks, and a workforce of as many as 300 people.

ALSO READ: Railways withdraw proposed rule for imposing excess baggage charges

If you think that it was all hard work than you are wrong. In order to save time, the official lifted the boxes from both sides and placed at the requisite location. The people in the area have been hailing the Railways achievement for completing the Limited Height Subway project in record time.

Watch the video here:

LEAVE A REPLY

Please enter your comment!
Please enter your name here

Share post:

Subscribe

Popular

More like this
Related

2024 Lok Sabha Polls: Phase 2 Polling Underway In 88 Constituencies | TOP UPDATES

New Delhi: The second phase of the 18th Lok...

IPL 2024: Patidar, Green, Karn Propel RCB To End Six-Match Losing Streak With 35-Run Win Over SRH

Hyderabad: Royal Challengers Bengaluru (RCB) delivered a collective team...

PM Modi Dials Italian counterpart Giorgia Meloni, Thanks Her For G7 Summit Invite

New Delhi: Prime Minister Narendra Modi had a telephone...